Coors Brewing Company, GOLDEN, CO
Mechanical Construction & Piping Retrofit Services
TRAUTMAN & SHREVE VALUE DELIVERED
- Time and Material
- Prime Contractor
- Mechanical Construction & Piping Retrofit Services
MECHANICAL SERVICES SCOPE OF WORK
The mechanical construction project required installation of over 15,000 linear feet of pipe that ranged in size from 1" to 10". The majority consisted of 6" stainless steel electro polished piping with over 320 existing tie-ins. The mechanical retrofit project included piping to the following equipment: Filtrox beer filters, Tuchenhagen beer, DI water, CIP manifolds, CIP buffer tanks, steam heat exchangers, dosing tanks and gas separators. Processes included were: carbon dioxide, DA water, beer, CIP (caustic), B-Water, A-Water, steam and condensate, and instrumentation.
BACKGROUND
Coors started in 1873. It now has annual sales exceeding 20 million barrels.
MECHANICAL CONSTRUCTION OBJECTIVES
To continually improve and update their facility, enabling them to keep up the beer brewin